Bridge on st. Bebel in Yekaterinburg turned into a tank road

“For the second week, like thousands of others, I have been driving along the street. Khalturin-Bebel to work in the center along the road, which is difficult to call a road, - writes in DK a representative of the company "" in the Urals, and in this case, just a resident of Yekaterinburg Roman Luchichev. - And I can’t understand why one of the busiest transport arteries of Yekaterinburg was broken and abandoned in obscene form by road builders ?! Why, because of their negligence, should thousands of citizens and guests of the city endure inconvenience - stand in a huge traffic jam and swallow dust, get nervous and get damaged in their cars?

According to Roman Luchichev, today, August 13, he witnessed an accident at the Khalturin-Gottwald intersection, which was probably caused by the condition of the road surface. He himself has already suffered: while driving along a problematic section of the road, a stone flew off into the windshield of Mr. Lukichev's car and broke it. “I am sure that this is not a complete list of material damage due to the disregard of the road workers and the authorities,” Roman Lukichev believes.

Recall that she listened to the complaints of motorists about the terrible state of the road surface on the bridge over the Iset along Bebel Street and. The contractor started the repair in early August. The repair of one of the lanes of Bebel Street, including the bridge, should be completed by 15 August. The bridge will be completely repaired by August 25, the press service of the administration of Yekaterinburg reports.

Work on Bebel Street is carried out mainly at night, which makes the bridge seem abandoned. GarantStroy specialists will have to replace almost 24,000 square meters of the roadway on Bebel Street, repair 2,700 square meters of sidewalks and restore 1,880 square meters of lawns.

Drivers in Yekaterinburg have long complained about the state of the Bebel bridge. In the spring, the photographer Ekamag drew attention to this section of the city network, who installed the “Pits” sign here.

The repair of another section of the Yekaterinburg road network is nearing completion: work on Mashinostroiteley Street from Cosmonauts Avenue to Pervaya Pyatiletki Square is already 90% completed. Here, 16,521 square meters of road surface will be replaced, 6,800 square meters of sidewalks will be replaced, and a new side stone will be installed. On August 20, the transfer of heating networks will be completed, after which the repair will end in as soon as possible. This was reported by the press service of the administration of Yekaterinburg.

It should be noted that road works in the center will be suspended during the celebration.

for Christmas and new year holidays Dnipro residents will be able to travel along the New Bridge in both directions. The overhaul will continue in March next year.

The new bridge will open on December 12. To do this, the contractor, Meister-Profi, will lay a temporary road surface at its own expense, which it will remove and complete the work on one side as early as March 2018. As soon as the permanent pavement is done, the second part of the bridge will be closed and repaired by the end of September next year.

On November 28, a meeting was held in the City Council of the Dnipro between the customer and the contractor for the repair of the New Bridge, deputies of the city council and journalists.

According to the deputy mayor of the Dnieper, Mikhail Lysenko, when work began on the bridge, they revealed much more problem areas than the project documentation provided. This is because the design documentation from the moment the bridge was built has not been preserved. “The work has increased 2.5 times,” Mikhail Lysenko said at the meeting. “There are no complaints about the quality of work.”

Yury Zubarev, the chief engineer of the project, has no special remarks about the underwater part of the bridge. Most of the problems arose with the beams. It is planned that at least 3 load-bearing beams will be replaced. Because of them, the bridge was declared emergency.

Since the beginning of the construction of the bridge, the contractor, Meister-Profi, has completed work worth UAH 53 million. The total overhaul of the New Bridge will cost UAH 250 million. As Petr Shmatchenko, head of the city's infrastructure department, said, with the start of work on the second side of the bridge, the cost of work may increase by up to 10-15%.

In addition, the contract also stipulates penalties for delays in the repair of the bridge. Their size, as Mikhail Lysenko stated, will be calculated later.

It is planned that after the repair the bridge will be 2.5 meters wider and will have 6 traffic lanes (3 on each side). The right and left sides will be separated by a concrete beam. According to the chief engineer, due to the fact that the bridge will be covered according to modern technologies the beam will not make the bridge heavier and the load will remain almost the same.

Until the end of August, the streets in the Bebelevsky Bridge area are doomed to stand in ten-point traffic jams. The thing is that on the eve of one of the spans of the overpass was closed for major repairs. The work is expected to be completed by August 25th.

– At first, traffic jams were only in one direction, now they completely closed the traffic in the direction of the Sorting, and everyone stood up. Kilometer traffic jams in both directions from morning to night. And it would be nice to have work going on there, but nothing has moved in 2 weeks ..

The competition for the repair of this section, like many others, was won by the Trest Uraltransspetsstroy company. From the documentation on the public procurement website, you can find out that the work will cost the budget 29.5 million rubles.

But in addition to the standard replacement of the top layer of asphalt, the estimate also includes repair of expansion joints (joints on the bridge), straightening of rain gratings without replacing them with new ones, as well as waterproofing of structures.

As the site found out, it is not Trest Uraltransspetsstroy that will directly repair the bridge, but a subcontractor, PGSCOM. This company specializes in the reconstruction of such objects.


- The bridge is in dire need of major repairs, as part of its structures have fallen into disrepair. It will last until the end of August, as some technology operations require a long time. For example, concrete should gain strength in 28 days.

According to him, after the replacement of the concrete pavement, the asphalt will stop collapsing. The new waterproofing will protect the structures from the harmful effects of precipitation. Previously, the overpass on Mashinnaya over the Bypass road was repaired in a similar way.


Khalturina stands before the overpass near the Tagansky row, and Tokarey - before Kraul.

Recall that the workers began to block On Sunday, the traffic on the overpass was completely closed. As a result, on the adjacent streets, even on a day off


Vladimir Putin would like the Russians to be able to use the automobile section of the Crimean Bridge this summer. The president said this during an inspection of the construction of the bridge, Interfax writes.

The builders announced their readiness to open traffic on the automobile part in May.

“An interesting object, powerful and even ahead of schedule. Of course, I would like people to be able to use it in the summer season," Putin said.

When will the Crimean bridge be opened?

On Wednesday, March 14, Russian President Vladimir Putin inspected the construction of the Crimean bridge and did not rule out that the crossing would be ready ahead of schedule. “I would like people to be able to use the Crimean bridge already in the summer season,” the head of state expressed his wish to the builders.

The bridge between Taman and Kerch should be opened for car traffic in December 2018, and trains will run on it a year later. The length of the transition from the Crimea to the rest of Russia will be 19 km. 11.5 of them will pass by land, including the island of Tuzla, 7.5 km - over the sea. This is the most long bridge in Russia and in Europe.

During the traditional address to the Federal Assembly on March 1, Vladimir Putin announced the imminent launch of automobile traffic. “In a few months, automobile traffic will open along the Crimean bridge, and next year, railway traffic. This will give impetus to the development of the peninsula and the entire Russian Black Sea region,” the President said.

Kerch bridge when will open, detailed information

The route of the distant Western bypass of Krasnodar has been approved. The new transport corridor will bypass the existing urban agglomeration and promising development zones, and provide a transport approach to the Crimean bridge.

The construction of the bypass will be carried out as part of the formation of the route "Motorway M-4" Don "(Krasnodar) - Slavyansk-on-Kuban - Temryuk - Bely - highway A-190 (Novorossiysk - Kerch Strait) - transport crossing through the Kerch Strait.

The far western bypass of Krasnodar will be a 1B technical category road with four lanes. The estimated speed will be 120 km/h. Three road interchanges, four bridges, ten overpasses will be built on the new highway with a length of 55 km, Avtodor said.

Crimean bridge, official site

The official site dedicated to the construction project of the Crimean bridge -